PROPOSED 2023/24 LOCAL TRANSPORT PLAN [LTP] CAPITAL PROGRAMME NEW ALLOCATIONS

 

Project/

Programme

Description

(see Footnotes below for explanation of symbols) 

2023/24 Proposed New

Allocation (£’000s)

2024/25

Indicative Allocation

(£’000s)

CAPITAL RENEWAL/MAINTENANCE

 

Maintaining links and routes to improve………….

 

Surfaces

Roads #

530

 

 

Pavement/Footways

400

 

Drainage

Replacement of failed gullies/soakaways

100

 

Bridges & Structures

Marine Parade retaining wall

100

 

 

Other

50

 

 

Seafront Highway Arches Renewal Programme

 

 

 

Shelter Hall

8

 

 

Arches 181-182

12

 

 

Duke’s Mound Arches

580

 

Asset Management

Surveys/update inventory/strategy evidence

55

 

CAPITAL RENEWAL/MAINTENANCE SUB-TOTAL

1,785

1,455

   

 

INTEGRATED/SUSTAINABLE TRANSPORT

 

Connecting people with……….

 

Education, Training & Learning

School Streets

100

 

 

School Travel Plan Measures *

15

 

SUB-TOTAL

115

 

Workplaces & job opportunities

Business Travel Plan Measures *

15

 

 

Personalised Travel Planning *

15

 

 

e-cargo bike accelerator project *

15

 

SUB-TOTAL

45

 

Parks, open spaces & the National Park

Rights of Way Improvement Programme

150

 

SUB-TOTAL

150

 

Interchanges

Cycle parking

25

 

 

Motorcycle parking

10

 

 

Accessible bus-stops

60

 

SUB-TOTAL

95

 

Improving neighbourhoods with……….

 

Road Danger Reduction

Collision/casualty/speed reduction sites

200

 

SUB-TOTAL

200

 

Air Quality measures

Rottingdean High Street – monitoring

5

 

 

SUB-TOTAL

continued……………./

5

 

Active travel measures

Pedestrian crossings – freestanding sites

200

 

 

Walking network – incl. dropped kerbs and handrails

50

 

 

Cycle network/Active Travel Fund Tranche 2 & 3 works

643

 

 

Active Travel Fund 4 **

100

 

 

BikeShare replacement programme

40

 

 

SUB-TOTAL

1033

 

Managing links and routes with……….

 

Technology & Travel Information

‘Intelligent/smart’ Traffic Signals – Phase 2

200

 

 

Real-time passenger information system

600

 

SUB-TOTAL

800

 

Connecting people and neighbourhoods with, and improving, the ..............

 

City Centre & Seafront

Valley Gardens:Phases 1 & 2 – monitoring

30

 

 

Bus Network Infrastructure (Western Road)

200

 

SUB-TOTAL

230

 

General allocations

 

‘Section 106’ works

Various sites +

50

 

Minor works

Scheme completion & scoping/Monitoring

30

 

SUB-TOTAL

80

 

INTEGRATED/SUSTAINABLE TRANSPORT SUB-TOTAL

2,753

3,083

TOTAL LTP ALLOCATIONS

4,538

4,538

 

 

 

Overall funding and budgetary sources/decisions for allocations:-

 

 

Government LTP and highway funding

 

 

LTP Integrated Transport Block Grant Allocation

3,083

3,083

LTP Maintenance Block Grant Allocation

1,455

1,455

Highway Maintenance Incentive Fund (based on Band 3 assessment)

364

364

Pothole funding

1,455

1,455

SUB-TOTAL

6,357

6,357

Other government funding

 

 

Active Travel Fund – Tranche 2

514

-

Active Travel Fund – Tranche 3

200

1,000

Bus Service Improvement Plan – first tranche

2,688

2,100

SUB-TOTAL

3,402

3,100

Council funding

 

 

Local safety schemes

53

-

Street lighting ‘Invest to Save’

810

1,000

Seafront heritage lighting renewal programme

1,050

1,000

Bus shelters (non-advertising sites)

23

-

Hove Station footbridge

250

250

School Streets

149

-

continued …………./

 

 

BikeShare replacement programme

1,000

215

Bike hangars

99

-

Citywide strategic transport model

800

-

Climate Action Fund transport projects

1,000

-

Carbon Neutral Fund – Liveable Neighbourhoods

1,000

-

Carbon Neutral Fund – traffic signal carbon reduction programme

400

-

Carbon Neutral Fund – e-cargo accelerator project

45

-

Carbon Neutral Fund – concrete road lifecycle extension programme

1,000

-

Carbon Neutral Fund – Western Road improvement

533

-

SUB-TOTAL

8,212

2,465

Other - Local Enterprise Partnership [LEP]

 

 

Local Growth Fund – Valley Gardens Phase 3 ***

4,600

4,000

SUB-TOTAL

4,600

4,000

GRAND TOTAL

22,571

15,922

 

Footnotes

#- sum will be increased through addition of government Incentive Funding allocation (£364,000 based on Band 3 self-assessment ranking) and Pothole funding (£1.455m), plus £1.0m from the CNF.  Works will include preventative measures to extend the lifecycle of roads.

 

+- to enable design and delivery of works associated with approved development.

 

* - local contribution to support DfT-funded Capability Fund projects

 

** - local contribution to ATF4 projects, subject to successful bid

 

*** -sums include council match funding for 24/25

 

NOTES

·      In many cases, costs indicated within the proposed programme are preliminary estimates. 

·      Expenditure on schemes may need to be increased, reduced or deferred during a financial year as information becomes available, such as survey results, tender returns or unforeseen engineering difficulties. 

·      The timing of construction works may be subject to network co-ordination with other council projects, development, utility companies, contractor availability and weather conditions.